The electricity network of two villages in Shamakhi has been rebuilt

The electricity network of two villages in Shamakhi has been rebuilt

As part of the investment project, “Azerishiq” OJSC has reconstructed the electricity network of Zarat Kheybari and Archiman villages of Shamakhi region.

“Report” reports about this with reference to the institution.

According to information, the village of Zarat Khaybari is located at an altitude of 2430 meters above sea level, 45 km away from the district center, in a difficult relief area. The energy farm of the village was in operation for more than 70 years. As a result of the reconstruction works, 2 complete transformer stations were installed in the village. About 5 km of 10 kV power line and about 6 km of 0.4 kV power line have been completely renewed.

10 and 0.4 kV power lines were canceled and more than 20 km of new cable lines were built in Archiman village. Three complete transformer substations have been installed in the village.

In both villages, subscribers’ meters were replaced with new ones.

The project covers more than 100 villages in the regions.